Pesocani

FYR Macedonia - reconstruction of the original plant from 1951.

Pesocani
Pesocani

Project review

The plant is located on the Pesocani River in the Pesocani village, near the Ohrid town, FYR Macedonia. The plant was built in 1951 and it is part of the distribution branch in the Ohrid town. The HPP Pesocani is a derivation type plant with a small dam and a side intake facility, 7 km long derivation channel, water chamber, 900 m long penstock and powerhouse.

The rehabilitation covered mainly installation of 4 new Pelton turbines (2 turbines per 1 generator), powerhouse substructure civil modifications, supply of new hydraulic governors, generators overhaul, new cubicle type substations 6 kV and 35 kV, complete automation of the units, substations 6 kV and 35 kV, and 10 kV distribution substation.

After the rehabilitation, the maximum power output of the power plant was increased from approximately 2.6 MW to 3.6 MW with expected annual generation increase from 10 300 to 12 200 MWh.

Provided services

HYDROPOL provided all engineering and management services necessary for the project, including main and detail design, contracting, supervision, project management and commissioning.

Main data

Country:FYR Macedonia
Built (year):1951
Output (kW):2 × 1760
Head (m):290
Capacity (m3/s)2 × 0.7
Completion (year):2008